Client Need
Following significant storm-related damage to the Virginia Creeper Trail, a federally owned National Recreation Trail in Southwest Virginia, the United States Forest Service initiated a major design-build reconstruction effort to restore public access, improve resiliency, and preserve the trail’s historic character. Spanning approximately 18 miles and incorporating 33 bridges, the project required accelerated delivery to support regional economic recovery and safely reopen a critical recreational corridor.
Kiewit Infrastructure South Co. required a geotechnical engineering partner capable of supporting a fast-paced, multi-disciplinary design-build environment while providing field exploration, geotechnical analysis, and bridge foundation design services for 22 of the project’s 33 bridges. The project demanded seamless coordination between field, laboratory, and engineering teams to keep bridge packages advancing on schedule.
How We Helped
UES provided geotechnical drilling and field investigations, laboratory testing, geotechnical analysis, technical memoranda, and micropile foundation design engineering for 22 bridge structures along the Virginia Creeper Trail corridor. Our team deployed resources across multiple offices to support the compressed design-build schedule and maintain efficient communication with the Kiewit project team.
UES integrated field exploration, laboratory analysis, and bridge foundation design workflows to streamline project delivery and support ongoing construction activities. Through responsive engineering support and coordinated technical services, our team helped reduce geotechnical risk while advancing resilient bridge designs suited to the challenging terrain and post-disaster conditions.

Project Highlights
- Project Length: Approximately 18 miles of reconstructed trail corridor
- Bridge Scope: 33 total bridges with UES providing foundation design services for 22 bridges
- Delivery Method: Accelerated post-disaster design-build project
- Services Provided:
- Geotechnical drilling and field investigations
- Laboratory testing
- Geotechnical analysis and technical memoranda
- Micropile foundation design engineering
- Technical Challenge: Multi-office team coordination under a compressed project schedule
- Infrastructure Focus: Restoration of federally owned recreation and transportation infrastructure
Client & Community Impact
UES helped support the restoration of a nationally significant recreation trail that plays an important role in Southwest Virginia’s tourism economy and outdoor recreation industry. By reducing long-term geotechnical and foundation risks, our team contributed to safer, more resilient infrastructure capable of supporting future public use.
The project also helped restore access for local communities and businesses that depend on trail-related tourism while preserving the historic character of the corridor. Through timely engineering support and coordinated project delivery, UES contributed to the accelerated reopening of the trail and the region’s broader economic recovery efforts.