Skip to content

Brazosport Water Supply Corp (BWSC) Harris Reservoir

Brazosport Water Supply Corp (BWSC) Harris Reservoir

Angleton, Texas
Client: Phillips Heavy Civil
Market Sector: Water Infrastructure
Role:Geotechnical Engineering & Construction Materials Testing Partner

Client Need

The Brazosport Water Supply Corporation (BWSC) Harris Reservoir project was developed to strengthen long-term water supply reliability and drought resiliency in Brazoria County, Texas. Constructed in partnership with BWSC and Dow, the reservoir was designed to increase Brazos River pumping and storage capacity available for municipal and industrial users during periods when river pumping may be limited or curtailed due to drought conditions.

The project includes construction of a 6.8-mile-long, 30-foot-tall earthen embankment utilizing approximately 12 million cubic yards of material and incorporating a low-permeability seepage barrier wall extending to depths of up to 150 feet. Due to the project’s scale, accelerated schedule, and intensive earthwork operations, Phillips Heavy Civil required an experienced geotechnical and quality control partner capable of supporting complex field investigations, laboratory testing, and continuous construction quality assurance activities throughout the project lifecycle.

How We Helped

UES provided geotechnical engineering and construction materials testing services for the BWSC Harris Reservoir project while serving as the overall project quality control partner on behalf of Phillips Heavy Civil. During the aggressively scheduled three-month geotechnical phase, UES deployed a 10-person field team supported by three drill rigs to perform deep geotechnical drilling and extensive subsurface investigations across the project site.

Our team completed approximately 12,000 linear feet of drilling to depths reaching 185 feet to evaluate subsurface conditions along the seepage barrier wall alignment and obtain samples for contractor treatability studies. UES also performed geotechnical mapping and laboratory soils testing within a 560-acre borrow area to support embankment construction operations.

To support the projected 43-month construction phase, UES established and operated an AASHTO and U.S. Army Corps of Engineers-accredited on-site soils laboratory while maintaining a six-person quality control technician staff. Our team provided continuous quality control support during high-volume earthwork operations exceeding 20,000 cubic yards per day across multiple placement areas, coordinating closely with the CMAR team, owner representatives, engineers of record, quality assurance personnel, and specialty contractors throughout construction.

Aerial view of a developing site with cleared plots, roads, and a large pond bordered by trees on the edge of a forested area.

Project Highlights

  • Reservoir Infrastructure:8-mile-long, 30-foot-tall earthen embankment
  • Earthwork Volume: Approximately 12 million cubic yards
  • Seepage Barrier Wall: Low-permeability wall extending to depths of up to 150 feet
  • Geotechnical Investigation:
    • Approximately 12,000 linear feet of drilling
    • Maximum drilling depths of 185 feet
    • Extensive laboratory soils testing and treatability support
  • Borrow Area Evaluation: Geotechnical mapping and testing across 560 acres
  • Construction Support:
    • Continuous QC support during peak earthwork production exceeding 20,000 CY/day
    • Six-person field QC staff during active construction
    • AASHTO and U.S. Army Corps of Engineers-accredited on-site soils laboratory
  • Project Coordination: Continuous collaboration with CMAR team, owner representatives, engineers, QA personnel, and specialty contractors

Client & Community Impact

UES is proud to support a critical water infrastructure project designed to improve drought resiliency and long-term water resource management throughout Brazoria County. By increasing water pumping and storage capacity from the Brazos River, the BWSC Harris Reservoir project will provide greater flexibility in managing regional surface water resources during extended drought conditions and future water supply challenges.

The project also supports continued industrial and community growth by helping secure reliable water access for BWSC customers, Dow, and other regional users. Through comprehensive geotechnical engineering, quality control, and construction materials testing services, UES contributed to the successful advancement of a major infrastructure initiative that will provide lasting environmental, economic, and community benefits for the region.