Construction Slide Causes Significant Delay and Added Costs

FIGURE 3 PHOTOGRAPH SHOWING THE RESULTING SLIDE FROM RIVERSIDE EXCAVATION
Presented herein is a case example of construction earth movement. The case exemplifies the significant effect such an event can have on the completion cost/time. This project involved the construction of a river intake facility to provide drinking water to area communities. To provide access to river water, two 3 ft. horizontal steel pipes were to be installed from the wet well, through the riverbank, and laid on the river bottom to the point of intake (see Figure 1).
FIGURE 1 PLAN SHOWING THE LAYOUT OF THE WATER INTAKE FACILITY
FIGURE 1 PLAN SHOWING THE LAYOUT OF THE WATER INTAKE FACILITY

The design of how the construction was to be accomplished was left to the bidding contractor without any significant technical review of how the installation would be done. The contractor chose to install the intake pipes by constructing two 5 ft. diameter cased horizontal bores from the wet well to near the riverbank face. The 3 ft. intake pipes would be installed inside these bores. The remainder of the intake pipe would be installed by subaqueous excavation from the riverside. Consequently, this would require underwater excavation into the riverbank to connect to the pipe installed form the wet well. This pipe intake construction methodology was allowed under the contract, and this methodology seemed feasible based on the available design borings which indicated that bedrock was at an elevation which would adequately support the overlying soils when the riverbank excavation was made (see Figure 2).

The contractor subaqueously advanced the excavation into the riverbank, but due to the limited visibility conditions, there was no warning that the soil portion of the slope was unknowingly undermined as the bedrock surface was significantly lower than anticipated (see Figure 2). Ultimately, this resulted in two successive slides (see Figure 3) and a halt in the project due to potential retrogressive movements encompassing the adjacent 4-lane state highway. During construction, none of the slope stability issues were analyzed by any of the project team members. After much time and expense, the project was eventually complete.

FIGURE 2 SOIL/ROCK PROFILE AT THE RIVERBANK
FIGURE 2 SOIL/ROCK PROFILE AT THE RIVERBANK
FIGURE 3 PHOTOGRAPH SHOWING THE RESULTING SLIDE FROM RIVERSIDE EXCAVATION
FIGURE 3 PHOTOGRAPH SHOWING THE RESULTING SLIDE FROM RIVERSIDE EXCAVATION