Foundation Treatment with Deep Mine Grouting

FIGURE 1 CROSS-SECTION OF FOUNDATION SCHEME USED TO RESIST LATERAL BUT LIMITED SUBSIDENCE GROUND MOVEMENTS

MEA, a UES Company, was selected to evaluate and recommend the most effective means to mitigate subsidence damage to the proposed DNR building in Springfield, Illinois. Based on a site investigation and subsequent analysis of the results, it was determined that the best solution would be combining foundation resistant features to the building with deep mine grouting. By doing this, the area of grouting was reduced to half the necessary volume, resulting in a savings of $1.5 million dollars. Grouting costs were further reduced by positioning the building over and adjacent to an expected lower excavation area. MEA worked with the structural engineers for the project to develop an appropriate foundation design for the project. A conceptual sketch showing the adopted design is given in Figure 1. 

FIGURE 1 CROSS-SECTION OF FOUNDATION SCHEME USED TO RESIST LATERAL BUT LIMITED SUBSIDENCE GROUND MOVEMENTS
FIGURE 1 CROSS-SECTION OF FOUNDATION SCHEME USED TO RESIST LATERAL BUT LIMITED SUBSIDENCE GROUND MOVEMENTS

To provide a cost-effective grouting plan, detailed drilling and borehole camera work were done in order to adequately identify the range of mine void conditions. The grouting of the 220 ft. deep mine was found to present a unique problem. Based on the exploration results the mine contained extensive piles of loose fallen roof debris on the mine floor up to 30 ft. high. These piles of roof debris consisted of large rock slabs to rock which had deteriorated to a soil consistency. Needless to say, this loose and softened debris—containing very coarse to fine particles—could not be relied upon to provide any overburden support. In other words, merely filling the more accessible mine voids with grout would not provide any support against mine collapse. By combining primary, secondary, and then tertiary grouting procedures with the use of appropriate grout mixes and the specified high grout pressures, the required grouted condition was achieved. This resulted in squeeze and compaction of the rubble while also maximizing penetration. The specified (low-shrink) low strength grouts had a wide range of flowability, ranging from efflux flow rate of 30 to 40 seconds to a 4-inch slump. A Type D set retarder additive was also specified. Performance specs were used in order to allow the contractor to design their own mixes and provide the most economic in-place grout costs. The mix used was determined in the field on a hole to hole basis using previous grouting results, void-rubble conditions from drilling, MEA borehole camera results, and on the grouting state (i.e. perimeter or infill grouting and if primary, secondary, or tertiary injection). Hole to hole grout flow was monitored by measuring changes in electrical resistance at mine level. Grout return has a distinct electrical resistance. Grout detection in open drill holes allowed these holes to be water flushed prior to the grout setting up and eliminated redrilling of those holes. Also a meter was manufactured to conveniently measure the cross-hole resistivity. Using these measurements, an indication of the presence of solid coal, grouted rubble, or an open mine void could be obtained (see Figure 2).

FIGURE 2 CROSS-HOLE RESISTANCE MEASUREMENTS
FIGURE 2 CROSS-HOLE RESISTANCE MEASUREMENTS

Probably the most important feature of this crosshole work is the ability to assess solid coal between the holes especially in older mines. Even if available, older mine maps typically do not show the proper pillar locations. Note on this project only main haulways are shown (see Figure 3). With cross-hole solid coal measurements unnecessary, injection holes can be eliminated and more confidence can be obtained in the layout of pillars and consequently in the grouting results. Overall the grouting beneath the building was first carried out on the perimeter followed by infill grouting. A total of 328 grout holes were drilled over 200 feet deep. This was about 20% less than anticipated. The project took 14,940 cy of grout which is close to the estimated quantity of 14,760 cy despite having incomplete mining geometries and having to account for the significant amount of rubble in the mine.

FIGURE 3 PLAN OF MINED-OUT AREA BENEATH SITE AND A BUILDING LOCATION
FIGURE 3 PLAN OF MINED-OUT AREA BENEATH SITE AND A BUILDING LOCATION

Geotechnical Investigation of Building Damage

Owner looking at his house with cracks in the side.

There are many reasons for building damage, some not as obvious as others. In fact, many engineers, architects, owners, and other associated parties do not appreciate or understand the geoforensic process when a structure may be damaged because of inadequate ground conditions. In addition to determining the specific cause(s) of the substantive error(s) that specifically caused the damage and recommending repairs, it may be important to assess responsible party(ies) leading to the damage. Reporting the latter can be an uncomfortable but necessary step. If insurance coverage is an issue, then the forensic investigation may extend into other technical questions regarding the causes or nature of the damage. It it important to note that the constructed product is the result of a multi-staged process. This process proceeds from the acquiring of input data used in design, to the design, then to the construction of the structure. Therefore, there are a number of factors which could contribute to the site construction problem(s) or damage. A simple example may be the best illustration of the geoforensic process. Keep in mind, however, that each case has its own particulars.

EXAMPLE CASE

Let’s take as an example the construction of a house. The owner, who is now living in the house, puts in an addition. Later he finds the basement and living quarters have substantial cracks in it and the owner wants to know what caused the damage, how to fix it, and who is at fault.

Owner looking at his house with cracks in the side.

THE DESIGN STAGE

Premise: The designer retains a geotechnical engineering company to perform a foundation investigation for a house that he has been contracted to design. The designer reads the geotechnical testing company’s report after their investigation and is told the foundation soil is a dry hard clay, but he still has questions. Consequently, he calls the testing company and asks the testing company if there are any water table problems and the testing company says they don’t think so. The foundation and basement are designed based on written and verbal information obtained from the testing agency. The designer (architect or engineer) uses some design procedures and building codes to determine foundation construction details and specifications.

Some Critical Questions: Did the designer use the appropriate procedures and building codes? (Examples would be a designer using antiquated formulas resulting in a substandard foundation or the designer improperly sizes the footing.) Did designer appropriately use all the relevant information at hand?

Premise: The owner decides to change the plan of the house. Plus, it is now winter and the designer verbally warns the owner that costs could be higher if the house is constructed then.

CONSTRUCTION-INSPECTION STAGE

Premise: This is an expensive house, so the designer has the inspector observe the foundation construction. The constructor and inspector work together to build a foundation to the designer’s specifications and plans. The basement is being dug out and there are seams of sand in the clay and water is flowing into the excavation. The inspector makes the contractor pump water out but this becomes difficult because the water freezes and therefore adds to the cost of construction. The clay is checked prior to pouring the footing by the inspector. The inspector puts in his report the clay is acceptable and the contractor proceed to builds on it.

Some Critical Questions: Did the contractor and the inspector appropriately follow the plans and specification of the designer? Was there additional verbal communication between all parties? Did the contractor properly construct the footing? Was the clay too soft in the area of damage to be supported by the specified footing size? Further, did the owner not tell the designer about the new addition?

FORENSIC INVESTIGATION STAGE

Scope: A damage investigation is undertaken. The geotechnical forensic engineer inspects and maps the construction, damage, and other relevant site conditions to understand the problem(s). Also, interviews are conducted with all available parties involved in the design, construction, and damage stages. Design and construction records are reviewed, as well as all available testimony. Once a sufficient understanding of the project is obtained by the geotechnical forensic engineer, the appropriate subsurface exploration and associated laboratory testing are performed to determine the actual conditions in the area of damage. After an analysis of the above information is completed, an expert evaluation of the acquired data is made.

Results of Premise: The geoforensic investigation found after inspection of the site, review of the project documents, and from project discussions that the main cause was probably related to foundation settlement and not from other causes (such as failure of a building member; poor construction; or the foundation clay becoming wet and swelling upward). Also, the designer appeared to appropriately use the reported geotechnical information, proper foundation design methods, and appropriate building codes.

The follow-up subsurface investigation revealed that a pocket of soft clay was present within the building area which was not found during the original exploration of the site. The soft clay did not meet the construction specifications outlined by the designer and consequently was inappropriately left below the foundation by the contractor and accepted by the inspector.

As can be seen from the above example geoforensic investigation, the correct findings require a multifaceted study. Also, a well-qualified forensic engineer performing such a study best understands the level and type of investigation effort necessary.

Investigation of a Roadway Failure

FIGURE 1 SOIL COMPACTED TO SPECIFICATIONS BECOMES TOO WEAK AT ALLOWABLE MOISTURE CONTENTS OR WHEN EXPOSED TO MOISTURE

A town in Missouri located on the banks of the Mississippi River demanded the construction of an earthen levee to protect itself from the floodwaters of the river. This required the construction of an asphalt bypass road for an existing state highway, as the proposed levee construction cuts across the highway into the adjacent limestone bluff. 

The contractor followed the design guidelines and took the care generally practiced in the field while constructing the bypass. There were rains and high river stages during the process of construction. The subgrade fill was compacted to required density. The engineers were satisfied with compaction test results and approved for asphalt paving. As soon as the paving started the subgrade started pumping. The asphalt truck became stuck, and had to be pulled out with a dozer. The asphalt paving was stopped when the asphalt trucks got stuck and created deep ruts. At this stage the engineers thought that the best remediation was to remove and replace the bypass. Even though the replaced bypass held up during second paving, the subgrade still pumped and the asphalt cracked and settled. Additional asphalt was used to bridge the subgrade and achieve the design lines and grades. 

An investigation was called upon to analyze the difficulties encountered during the construction of the bypass. The site was inspected and documented and subsurface conditions were mapped and sampled. Detailed assessment of road conditions and associated plans and specifications were done to determine the cause(s) of construction difficulties. 

Forensic testing was conducted on the representative samples collected from the field. Based on the laboratory results the soils used for road fill and natural deposits were reclassified. These soils exhibited unusual characteristics for a silty or clayey soil. In moist conditions, the soils appeared sandy as the individual soil grains appeared to aggregate. Also the soils exhibited unusual compaction properties. 

It was discovered from the laboratory testing that there was a dramatic decrease in soil strength when the fill or subgrade soil was compacted at wetter allowable moisture contents or when the soil compacted to specifications became exposed to moisture (see Figure 1).

FIGURE 1 SOIL COMPACTED TO SPECIFICATIONS BECOMES TOO WEAK AT ALLOWABLE MOISTURE CONTENTS OR WHEN EXPOSED TO MOISTURE
FIGURE 1 SOIL COMPACTED TO SPECIFICATIONS BECOMES TOO WEAK AT ALLOWABLE MOISTURE CONTENTS OR WHEN EXPOSED TO MOISTURE

Therefore, the decline in the performance of the bypass road is linked to the moisture-induced softening of previously compacted embankment subgrade soils. It was found that the exposure to moisture was exacerbated by the upward movement of groundwater given the geologic setting. The results of laboratory testing explained how the fill and subgrade prepared to the plans and specifications resulted in the road failure realized in the field. Although the compacted roadway foundation was prepared under the engineer’s approval it was too unstable for the installation of the asphalt pavement when exposed to moisture. 

During construction a number of observations were made of upward migration of groundwater, surface springs, and artesian conditions. However, the preconstruction groundwater levels at the site were considerably lower. An analysis of the hydrogeologic conditions helped in unraveling the story behind this moisture softening of the compacted subgrade and fill. The bluff which is adjacent to the site is made of solutioned limestone and acted as a groundwater recharge area (see Figure 2). 

FIGURE 2 HYDROGEOLOGIC PROFILE OF THE SITE
FIGURE 2 HYDROGEOLOGIC PROFILE OF THE SITE

During heavy rains, the groundwater levels rose in the bluffs which in turn caused a rise in the hydraulic head in the sand layers lying underneath the silts/ silty fine sands in the foundation and embankment. The plastic lean clays and fat clays below the foundation subgrade appear discontinuous and did not provide an impermeable barrier for the upward movement of the groundwater. Also the silty embankment and foundation soils are conducive to significant capillary rise and are extremely vulnerable to pumping action which brings the freewater to surface in response to traffic loads. 

The results of this testing combined with the geologic setting explained how the fill and subgrade prepared to the plans and specifications resulted in the road failure realized in the field. Although the compacted roadway foundation was prepared under the engineer’s approval it was too unstable for the installation of the asphalt pavement when exposed to moisture. The asphalt crumbled because of the unstable fill and subgrade as the roadbed was too soft to support necessary construction traffic.

Borehole Radar Determines Solid Coal and Mined-Out Areas

FIGURE 1 MEA BOREHOLE RADAR SYSTEM: ANTENNAS BEING LOWERED INTO BORINGS IN ORDER TO CONDUCT A CROSS-HOLE SURVEY

MEA, a UES Company, was asked to determine the effects of mining beneath a proposed roadway structure. In order to determine the subsidence potential and the magnitude of the mine stabilization costs, it is important to know whether underground mining is present, and if so, to what extent. The site investigated had the potential to have mining in three different coal seams. The Illinois Coal seams in question were the No. 7, No. 6, and the Seelyville ranging in depth from 70 to 300 ft. 

Because of inaccuracies which exist in old abandoned mine maps and since up to 10 years of mining occurred after the date of the available No. 7 Coal mine map, cross-hole radar surveys were performed in order to determine the actual extent of mining. The borehole radar was also used to determine whether the No. 6 and Seelyville seams were mined below the site.

Borehole Radar System:

MEA’s borehole radar system which was used on this project is shown in Figure 1. A borehole radar works particularly well for detecting solid coal and void areas because a coal seam is bounded above and below by materials with different electrical properties than that of the coal. Because of this, it is possible to use electromagnetic (radio) waves to detect anomalies in the coal seam. Materials such as shale, claystone, and mudstone generally have low resistivities on the order of 50 to 10,000 ohm-cm. Coal generally has a much high resistivity on the order of 20,000 to 80,000 ohmcm. The dielectric constant of coal is generally lower than that of roof and floor materials, in the range of 5 or 6 as compared to 10 or greater for the roof and floor. These differences in electrical properties of the materials produce boundary conditions at the interfaces of coal-roof and coal-floor that allow a radio signal to be “trapped” in the coal seam and to propagate through the coal as in a waveguide. Therefore, a radio signal in solid coal will travel with less attenuation than in free space.

If two antennas are lowered down boreholes to the coal seam, a radio signal transmitted form one antenna will transmit through the coal to the receiving antenna with a certain attenuation rate (see Figure 2a)/ In a homogeneous coal seam this rate will be determined by the characteristics of the coal such as resistivity, moisture content, and coal seam thickness. In this case, the attenuation will be a function only of the distance between the antennas—the greater the distance, the weaker the signal

The presence of a mined-out area (void) in a coal seam is an anomaly and will produce a greater attenuation for a ray path through or in the vicinity of the void (see Figure 2b). If the void is close to but not directly in the ray path, there will be a small increase in attenuation of the signal.

By measuring the strengths of many signals through various ray paths between pairs of boreholes drilled through a coal seam, the attenuation rate of solid coal for the area can be established and compared with the other measured attenuations to determine which ray paths pass through solid coal and which pass through or near mine voids. By this methods, the likelihood of the presence of a void in a ray path can be determined.

Results:

In about 8 days of field work, a total of 51 ray paths were performed. The travel distances between boreholes were up to 240 ft. which is significantly greater than that achieved with surface ground penetrating radar (GPR). The cross-hole surveys found solid coal as well as flooded mine voids with and without rubble.

FIGURE 1 MEA BOREHOLE RADAR SYSTEM: ANTENNAS BEING LOWERED INTO BORINGS IN ORDER TO CONDUCT A CROSS-HOLE SURVEY
FIGURE 1 MEA BOREHOLE RADAR SYSTEM: ANTENNAS BEING LOWERED INTO BORINGS IN ORDER TO CONDUCT A CROSS-HOLE SURVEY
FIGURE 2 BOREHOLE RADAR SYSTEM SHOWING RAY PATHS AND ATTENUATION BY A VOID IN THE COAL SEAM
FIGURE 2 BOREHOLE RADAR SYSTEM SHOWING RAY PATHS AND ATTENUATION BY A VOID IN THE COAL SEAM

The results obtained in the No. 7 Coal seam are summarized in Figure 3. There were 41 ray paths taken in this coal seam. All the measurements except two (TL-2/TL-6 and TL-2/ TL-20) confirm the mine outline. In order to assess the indication of mining between TL-3 and TL-6, a supplement boring was drilled (TL31). Measurements from this hole showed solid coal. Consequently, it was concluded that mining was in the vicinity of TL-3/TL-6 ray path but it did not proceed southwest (see Figure 3). The other anomalous ray path measurement indicated no mining where it clearly existed based on the mine map and a number of other ray path readings. This anomalous reading was attributed to electrical resonance form the relative orientation of steel roof support (probably left in the main rooms in this section of the mine) and the ray path.

In summary, the borehole radar subsurface investigation:

  • Validated that the mine map in the No. 7 Coal was fairly accurate despite its age (1888),
  • Found no mining in the No. 6 Coal, and
  • Found an area of unknown mining at a depth of about 300 ft. in the Seelyville Coal Seam which was verified by subsequent drilling.
FIGURE 3 RAY PATHS BETWEEN BORINGS MEASURED WITH BOREHOLE RADAR IN THE NO. 7 COAL AT THE PROJECT SITE
FIGURE 3 RAY PATHS BETWEEN BORINGS MEASURED WITH BOREHOLE RADAR IN THE NO. 7 COAL AT THE PROJECT SITE

Frozen Fill Causes Building Damage

FIGURE 6 GRAVEL BEING INSTALLED IN BUILDING PAD AND AGAINST FROZEN FILL SLOPE
FIGURE 1 DEFORMATION PATTERNS AT THE FRONT OF THE STRUCTURE
FIGURE 1 DEFORMATION PATTERNS AT THE FRONT OF THE STRUCTURE
FIGURE 2 SURFACE TOPOGRAPHY OF PARKING LOT SOUTH OF THE BUILDING AND LOCATION OF TEST PITS/STRIP AND EXPLORATORY BORINGS

Shortly after construction the ground beneath the front of a food store in Minnesota settled and moved laterally away from the building. This building behavior is shown in Figure 1. Also, significant movement was experienced in the parking lot in front of the store. The resulting damage mainly consisted of structural distortion of a canopy structure which supports second floor office facilities, significant cracking and separations in the masonry walls, racked store openings, as well as uneven settlement causing significant ponding and adverse grades in the parking lot. 

The maximum measured settlement was up to 3.5 ft. and was located in the parking lot. A topographic map prepared across the project site is shown in Figure 2. By analyzing design and post-settlement grades, the building experienced as much as 0.5 ft. of differential settlement. An important feature of the movement was the determination that basically a settlement through had developed adjacent to the store. A section across the trough in the approximate area of maximum settlement is depicted in Figure 3. To determine the source(s) of the ground movement which resulted in the building damage, a total of 4 test pit/strips and 10 borings were drilled (see Figure 2). 

Prior to development of the shopping center (which included the food store) there were fairly dramatic topographic and geotechnical conditions north to south across the site with differences in elevation of about 90 ft. This required cuts of up to 40 ft. into hard igneous rock to the north and fills more than 30 ft. to the south over some areas which contain significant amounts of peat and organics to bring the food store 18 ft. into hard rock in back of the store and fill up to about 25 ft. in the front. The fill was to consist of gravel from crushed blast rock sloped down to native soils at a specified 1:1 slope after any organics were removed. In the parking lot to the south, 8-10 ft. of residual cut soils were placed over the lower elevation swamp-like materials. 

On top of the residual soil fill shot (blast) rock (mainly boulder and cobble sized from the rock cut) was installed to about 1 ft. below top of pavement. The shot rock was covered with geofabric, subbase stone, and then asphalt (see Figure 4). 

FIGURE 3 SECTION A-A SHOWING SETTLEMENT IN FRONT OF BUILDING AND THROUGH PARKING LOT
FIGURE 4 DESIGN CROSS-SECTION ACROSS THE BUILDING SITE
FIGURE 4 DESIGN CROSS-SECTION ACROSS THE BUILDING SITE
FIGURE 5 AS-BUILT CROSS-SECTION DETERMINED FROM THE GEOSCIENCE INVESTIGATION
FIGURE 5 AS-BUILT CROSS-SECTION DETERMINED FROM THE GEOSCIENCE INVESTIGATION

It was initially thought that the presence of peat to the south was the likely cause of ground movement affecting the building. While it appeared to be mainly the cause for settlement to the south in the parking lot, the exploratory work uncovered the main cause for the resulting damage to the store was thawing of frozen residual soil fill within the influence zone (and building pad) of the structure. The location of this material is shown in the cross-section in Figure 5. Based on our forensic studies this frozen material was left within the building pad and froze when the north construction slope of this fill was exposed to winter conditions because the building pad gravel had not been placed over it in time. This can be seen in the photograph looking along this construction slope in Figure 6. The photograph was taken by a local geotechnical inspection engineer.

FIGURE 6 GRAVEL BEING INSTALLED IN BUILDING PAD AND AGAINST FROZEN FILL SLOPE
FIGURE 6 GRAVEL BEING INSTALLED IN BUILDING PAD AND AGAINST FROZEN FILL SLOPE

Hard Excavation Dispute

FIGURE 3 EXCAVATOR FULCRUM ACTION WHICH DETERMINES DIGGING FORCE

MEA, a UES Company, was selected by a Pennsylvania earth moving contractor and his attorney to investigate his dispute with the owner over the hard excavation quantity. The project involved installing the third phase of a major sewer line mainly in an open cut in soil and rock. Phase III was about 2 miles long (see Figure 1). Figure 2 shows the excavator attempting to rip rock in the bottom of the trench excavation. The hard excavation quantity measured and reported by the owner and the contractor were drastically different. The owner considered the contractor paid in full at about 3,700 cubic yards. The contractor reported about 12,000 cubic yards.

FIGURE 1 SEWER LINE ALIGNMENT ALONG THE OHIO RIVER

Under the contract specification, hard excavation was basically stated as: “… “Hard” excavation shall include materials that cannot be effectively removed by a late model hydraulic excavator with greater than 160 flywheel horsepower, and equipped with a rock ripping bucket. Hard and compact material such as claystone or relatively soft or disintegrated rock will not be considered as such because of the intermittent use of hydraulic hammers to break up rock or concrete merely to increase production…” MEA’s forensic investigation of the above dispute included the review of project documents and depositions, data reduction, and evaluation of engineering design and field reports, as well as project discussions with construction personnel. Based on this investigation MEA found that the engineer neglected to count a significant quantity of material from the own records which amounted to approximately an additional 1,000 cubic yards. After this difference was brought to their attention the owner recognized the error; however, a significant difference in measured amount of hard excavation still existed between the contractor and owner.

FIGURE 2 PICTURE SHOWS CONTRACTOR USING A 300 HP EXCAVATOR FOR RIPPING ROCK. CONTRACT REQUIRED 160 HP EXCAVATOR TO DETERMINE HARD EXCAVATION QUANTITIES
FIGURE 2 PICTURE SHOWS CONTRACTOR USING A 300 HP EXCAVATOR FOR RIPPING ROCK. CONTRACT REQUIRED 160 HP EXCAVATOR TO DETERMINE HARD EXCAVATION QUANTITIES
FIGURE 3 EXCAVATOR FULCRUM ACTION WHICH DETERMINES DIGGING FORCE
FIGURE 3 EXCAVATOR FULCRUM ACTION WHICH DETERMINES DIGGING FORCE D

MEA further determined that the main basis for the dispute in measuring hard excavation lay in the contract definition. MEA found:

  • Based on their interpretation of hard excavation specification at the time of bid the contractor assumed that hard excavation was encountered whenever rock could not be excavated freely and required use of a hoe ram. A more stringent standard than expected was applied during construction by the Owner’s Representative.
  • As pointed out by MEA, variant field assessment of hard excavation by all parties (individually and as a group) involved in this project is symptomatic of an ill-defined and defective specification of hard excavation. Consequently, there are many valid interpretations of what hard excavation is. For example, the ripping force of an excavator can vary significantly even if it has the same horsepower. Analogous to a fulcrum, the stick length of the hoe excavator plays a critical role. In other words, the shorter the stick, the greater the digging force (see Figure 3).
  • Further, the actual method of excavation used to remove rock was incompatible with the way hard excavation was to be measured per the specifications. For example, the contractor used a 300 hp excavator compared to the 160 hp machine required by the contract to determine hard excavation. After depositions and trial, the court ruled in the favor of our findings and awarded the contractor his measured quantity with damages.

Improvement of Mine Support Saves Pipeline from Subsidence Event

FIGURE 1 INITIAL LAYOUT OF PILLAR SUPPORT CONTEMPLATED OVER THE PIPELINE

A mining company proposed underground extraction of some coal reserves. Unfortunately, several significant pipelines traversed over the proposed mined-out area. Because of the potential for unplanned ground subsidence, the pipeline companies became concerned about possible subsidence damage and pipeline safety. In order to have an independent evaluation to determine if sufficient mine support would be left after coal extraction; a number of the pipeline companies retained the geotechnical engineering services of MEA, Inc., a UES Company. Based on review of the available information and the proposed mine design, MEA determined that the risk for subsidence was too great. The mining company said sufficient permanent support would be provided by the planned pillars. However, concern for pipeline damage from short or long-term mine subsidence after the mining was complete still existed. As a result of the concern for pipeline safety from the proposed subjacent mining, a consortium of pipeline companies brought legal action. The court determined that mediation was appropriate.

FIGURE 1 INITIAL LAYOUT OF PILLAR SUPPORT CONTEMPLATED OVER THE PIPELINE
FIGURE 1 INITIAL LAYOUT OF PILLAR SUPPORT CONTEMPLATED OVER THE PIPELINE
FIGURE 2 FINAL LAYOUT OF PILLAR SUPPORT USED BENEATH THE PIPELINE
FIGURE 2 FINAL LAYOUT OF PILLAR SUPPORT USED BENEATH THE PIPELINE
FIGURE 3 MINE SUBSIDENCE WITH SURFACE CRACKING TO LIMIT PILLAR SUPPORT FOR PIPELINES
FIGURE 3 MINE SUBSIDENCE WITH SURFACE CRACKING TO LIMIT PILLAR SUPPORT FOR PIPELINES

Pursuant to this order, MEA met with the mining company. A number of “one on one” technical discussions took place. As a result, considerably wider pillars were left to support the pipeline. The improved support can be seen by comparing Figure 1 to Figure 2. Figure 1 depicts the mine plan approved by the state regulatory agency while Figure 2 is the layout used after discussions with MEA. Note that the supported pillars were made about twice their intended width. 

The added support provides significantly greater methodology used and recognized by the State. The concern was summarized in a report and pertains to the added support which provides significantly greater protection for the pipelines involved. MEA had a further concern, however, regarding the design methodology used and recognized by the state. The concern was summarized in a report and pertains to the softening of the mine floor (especially from pooling water). Based on computer modeling results, MEA found the effect of floor softening to be substantial, and recommended it be accounted for in the design. 

Despite MEA’s warning, sludge (a water suspension of coal processing waste) was injected into the mine. The injection of sludge was followed by mine collapse and subsidence (see Figure 3). MEA believes the mine floor was softened by the water in the sludge. The now softened floor couldn’t hold up the coal pillars, resulting in a massive collapse of the mine. The subsidence propagated up to the ground surface with ground cracking towards its limit. As can be seen in Figure 3, the added support has suppressed the subsidence from progressing under the pipeline. 

In summary, from the “one on one” discussions with the mine design engineer, MEA was able to provide the coal company an engineering understanding of the concerns for mine stability. The result was the added protection to the pipeline from increasing the width of support pillars. Ultimately, these wider support pillars provided enough resistance to suppress an adjacent massive mine collapse from propagating into the Zone of Influence of the pipeline.

Mitigation of Mine Subsidence Risk to a Prison Complex

FIGURE 1 EXAMPLE OF SUBSIDENCE RISK MAP FOR A STRUCTURE

Readers of our mine backfilling project (see Issue 1 of Engineering UPDATE) had a number of questions regarding the site evaluation process. Consequently, this UPDATE discusses the process that was undertaken to mitigate the effects of mine subsidence on the proposed prison structures above old abandoned underground workings. The site for the proposed prison complex purchased by the state of Indiana was located in west-central Indiana and was undermined by an old abandoned room-and-pillar mine. This site was chosen because of its relatively low cost (as a result of being undermined), significant acreage, politically advantageous location, and possible other reasons. The original plan consisted of one phase of construction.

Based on a study of the mine map and subsurface verification of the extent of mining, it was determined that all prison buildings and important structures could be placed above solid coal to the north. The subsurface verification program consisted of drilling a number of holes and performing crosshole electromagnetic surveys. One masonry building, however, was located near mine works that still contained significant mine voids. The subsurface investigation identified the only viable ground movements to be associated with this structure were the milder reaches of the draw zone in lieu of costly design for the various more severe subsidence scenarios. The subsidence potential was estimated based on empirical data and the building was designed accordingly to be mine subsidence resistant. 

Because the land had already been purchased and the ability to use the newly constructed facilities, the State of Indiana decided to construct a Phase II prison complex adjacent to and just south of the Phase I complex (see Figure 1, Issue 1). This complex would be directly above the underground workings. The first stage of design was to minimize by positioning the exposure of significant structures to subjacent mining, assuming the mine map was sufficiently accurate. Consequently, an extensive subsurface investigation program similar in nature to Phase I was then undertaken mainly to:

  1. Ascertain whether or not mine areas where buildings would be located were already collapsed and thus only nominal, if any, subsidence could occur in the future; and
  2. Verify the presence of solid coal areas within the mine as indicated on the mine map.
FIGURE 1 EXAMPLE OF SUBSIDENCE RISK MAP FOR A STRUCTURE
FIGURE 1 EXAMPLE OF SUBSIDENCE RISK MAP FOR A STRUCTURE
FIGURE 2 EXAMPLE OF ESTIMATED SUBSIDENCE PROFILE FOR SMAX(2) ZONE WITH A 30° DRAW ANGLE (SEE FIGURE 1)
FIGURE 2 EXAMPLE OF ESTIMATED SUBSIDENCE PROFILE FOR SMAX(2) ZONE WITH A 30° DRAW ANGLE (SEE FIGURE 1)

Based on all the information gathered, subsidence profiles were developed from an empirical database of subsidence events in the Illinois Coal Basin. For each important structure that could be potentially affected by future subsidence movement, preliminary subsidence resistant designs were completed using the expected level of potential subsidence movement. Figures 1 and 2 illustrate an example of the subsidence risk maps provided for each structure. The estimated costs to make each structure subsidence resistant were found to be significant.

As an alternative to providing each exposed building with subsidence resistant construction, the possibility of mine backfilling was explored. Structure locations were moved somewhat to obtain the most surface support that could be obtained for the area of mine backfilled. As a result, three mine areas were identified for backfilling. The estimated cost for the backfilling was found to be by far the most cost-effective solution for the structures where little damage could be tolerated. Furthermore, the mine backfilling solution resulted in nominal risk of any surface subsidence above the areas backfilled.

Response of House Foundations During Earthquake

FIGURE 3 HOUSE THAT WAS NOT BOLTED DOWN WAS KNOCKED OFF ITS FOUNDATION DURING THE LOMA PRIETA EARTHQUAKE

The Loma Prieta Earthquake occurred in the Santa Cruz Mountains about 60 miles south of San Francisco on October 17, 1989 at 5:04 pm. The quake registered 7.1 on the Richter Scale and was located between the towns of Boulder Creek to the northwest and Watsonville to the southeast (see Figure 1).

FIGURE 1 LOCATION OF THE LOMA PRIETA EARTHQUAKE AND THE REGIONAL FAULTING FAULTING CHARACTERISTICS
FIGURE 1 LOCATION OF THE LOMA PRIETA EARTHQUAKE AND THE REGIONAL FAULTING FAULTING CHARACTERISTICS
FIGURE 2 TYPICAL RESIDENTIAL FOUNDATION TYPES
FIGURE 2 TYPICAL RESIDENTIAL FOUNDATION TYPES

Presented here are overall observations on the response of residential foundations to the Loma Prieta earthquake. These observations are based on field inspections across the entire damage area affected by the quake, review of numerous engineering investigations and repair recommendations, and many detailed interviews conducted with geotechnical and structural engineers with extensive experience in the EQ damage to the residential structures.

Foundation damage from the Loma Prieta Earthquake was observed as the result of induced ground movement as well as from literally shaking. EQ-induced ground movements which most commonly resulted in residential foundation damage were mainly the result of landsliding, soil densification, and liquefaction. The occurrence of these different phenomena mainly depended on geologic setting, geotechnical properties of the ground, and the magnitude of the shake. Overall, perimeter foundation systems were found to be the most sensitive to damage. 

Although the shaking damage was less significant than the ground induced damage, there were certain more prominent damage scenarios including tensile cracking of concrete stem walls and footings, floor sliding on foundation, racking of cripple walls, and racking post-and-pier foundations. In the Loma Prieta earthquake some houses were knocked completely off the foundation (see Figure 3).

Hillside homes resting on post-and-pier foundations present a structural situation where shaking is accentuated. This condition results because the entire residential structure is top heavy, likened to a heavy weight on a stick that is shook at its base. Consequently, because the posts are typically not sufficiently braced nor fixed into the ground, they become significantly racked and displaced as the house shook. Figure 4 is a photograph of this type of racking damage.

FIGURE 3 HOUSE THAT WAS NOT BOLTED DOWN WAS KNOCKED OFF ITS FOUNDATION DURING THE LOMA PRIETA EARTHQUAKE
FIGURE 3 HOUSE THAT WAS NOT BOLTED DOWN WAS KNOCKED OFF ITS FOUNDATION DURING THE LOMA PRIETA EARTHQUAKE
FIGURE 4 RACKING OF POST-AND-PIER FOUNDATION ON MOUNTAIN SIDE FROM SHAKING
FIGURE 4 RACKING OF POST-AND-PIER FOUNDATION ON MOUNTAIN SIDE FROM SHAKING

Soil Provides Poor Road Construction Support

FIGURE 1 UNSOAKED AND SOAKED CBR VALUES VERSUS MOISTURE CONTENT AT STANDARD COMPACTION FOR SUBGRADE SOIL

The new concrete pavement for an airport facility in Memphis, TN had an abnormal and alarming amount of cracking. Also, there were significant difficulties during construction in preparing the subgrade. As a result of these construction and performance problems, MEA, a UES Company, was requested to conduct a forensic geotechnical investigation.

Loess (a wind-blown soil deposit) was the immediate subgrade support for the about 16 acres of new pavement. Upon visual examination, this loess subgrade appeared to be moist and a typical loess soil with significant amount of silt. In the lab, however, when the above loessal soils were tested across the typically recommended and specified compaction ranges, this soil was found to have extremely detrimental characteristics for pavement support and construction. In addition to having low bearing strength at both modified and standard Proctor compaction limits, there was also significant swell. Also, the soaked bearing strengths for this soil were always lower than the recommended range for pavement design.

FIGURE 1 UNSOAKED AND SOAKED CBR VALUES VERSUS MOISTURE CONTENT AT STANDARD COMPACTION FOR SUBGRADE SOIL
FIGURE 1 UNSOAKED AND SOAKED CBR VALUES VERSUS MOISTURE CONTENT AT STANDARD COMPACTION FOR SUBGRADE SOIL
FIGURE 2 COMPARISON OF ELEVATION PROFILES ACROSS DAMAGED AND NEARBY UNDAMAGED CONCRETE PAVEMENT SECTIONS
FIGURE 2 COMPARISON OF ELEVATION PROFILES ACROSS DAMAGED AND NEARBY UNDAMAGED CONCRETE PAVEMENT SECTIONS

Without testing at the compaction limits of +95%, the results can be deceiving and produce exceedingly high soaked CBR values with no evidence of the soil’s swell potential. This was especially the case with regard to this loess. From soaked bearing strength testing it was found that this soil had an egregious sensitivity to the compacted moisture-density where the peak strength was up to 10.9-fold greater than at the 95% standard compaction limits (9.4 ave). For example, see Figure 1 which depicts the drop in strength when the soils became soaked.

The very bad engineering properties of these subgrade soils can be attributed to the significant amount of smectite present in the loess. From X-ray diffraction tests the <1 μm fraction of the loess was found to have clay consisting of an average 40% smectite. Clay minerals are known for their dramatic expansion with water absorption.

The use of a subgrade soil with this amount of smectite resulted in a myriad of construction difficulties. Shortly after the pavement was placed, significant damage was evident. The pavement cracking became significantly worse in less than a year’s time. Differential surface elevations measured across the concrete pavement demonstrates the effects of the swelling/shrinking and softening process of the pavement subgrade which is accompanied by soil moisture change (see Figure 2). Also, the soft to hard subgrade stiffness determined from falling weight deflectometer tests in correspondingly wet and slightly moist areas validated this soil behavior.

Classification of the swell potential of soils based merely on plasticity index values could be misleading. In fact, pavement construction soils classified by plasticity with even a low to medium swell potential could have a significant impact on the final product. The effect of swell on damage is a function of structure type and the construction activities. Soil swell also causes changes in grades during construction—and if unsuspected—results in thinner pavement courses than specified, not to mention the future performance problems of the pavement.